PROJECTS > Construction and Completion of 64 ML R. C. Water Reservoir (WR 2) and Other Associated Works (Packag

Project Background
PUTRAJAYA was in the limelight of media and political attention with its development as the New Federal Government Administrative Centre and intelligent city for the centre of information technology. Under the Putrajaya Masterplan - UDG Development Plan, PUTRAJAYA was designated with a massive area of approximately 4,400 hectares; the Core Island consisting of Government Buildings, Parks, Commercial and Residential areas.

With the above massive planned development, there was an urgent need to cater for the water supply needs of the increasing population.

Asia Baru Construction Sdn. Bhd was entrusted to construct and complete a 64 ML Reinforced Concrete Reservoir and other associated works at Precinct 18. The associated works included: -

> Access road leading to the reservoir site.

> Incidental excavation for the reservoir.

> Drainage works within the reservoir site and access road.

> Reservoir pipeworks within the reservoir site.

> Electrical and instrumentation works such as compound lighting and instrumentation for valves and flow meter and the SCADA system for the operation of the valves.

> Construction of a metering hut for housing of MCC and instrumentation panel.

> The supply and laying of rising (1300mm diameter M. S. pipes) and distribution mains (1000mm diameter and 1200mm diameter M. S. pipes) including valves and fittings.
Project Information
Client / Owner: Putrajaya Holdings Sdn. Bhd.
Consultant: Sepakat Setia Perunding Sdn. Bhd.
Main Contractor: Asia Baru Construction Sdn. Bhd.
Sub-Contractor: N/A
Date of Commencement: 30th April 2001
Date of Completion: 30th October 2002
Project Methodology
All the construction works in Putrajaya development is closely monitored by Project Management Team (PMT) i.e Kuala Lumpur City Centre Berhad. Due to the huge scale of development and the needs to coordinate the construction activities of contractors, the PMT had established various standardised procedures and requirements applicable to all contractors. Amongst there were : -

> Project scheduling and monitoring

> Project quality planning

> Logistic planning

> Environmental management planning

> Health and safety planning

> Security planning

Asia Baru Construction Sdn. Bhd., an ISO 9002:1994 accredited company at the time had given particular emphasis to the above procedure and proceeded with the planning immediately upon receipt of the Letter Of Award. Within two (2) weeks after the commencement of the Contract, all the necessary documented procedures and plans were forwarded to PMT and majority of these plans were approved within the subsequent week, thus enable the commencement of physical works at the site. Throughout the implementation period, the plans were strictly followed and all the above contractual requirements were complied.

The project was implemented smoothly and all the works were completed within the Contract Period, despite many variation/additional works been issued by PMT. Again, Asia Baru Construction Sdn. Bhd. is able to meet all the Clients requirement and complete the project successfully on time despite having to work under very stringent requirement and supervision.