PROJECTS > Raw Water Augmentation System For Wangsa Maju Treatment Plant

Project Background
The year was 1998 and the worldwide weather pattern was thrown into total chaos by arguably the most serious El Nino effect of the century. The unusually prolonged dry months had resulted in a water crisis unprecedented in scale in the history of Kuala Lumpur and Selangor.

Cries of help fell into the ears of the highest level of administration in the Federal Government. JKR (Cawangan Bekalan Air) responded emphatically by awarding a fast-track turnkey contract to Biwater Shellabear (M) Sdn. Bhd. to design and construct a raw water augmentation system for the new Wangsa Maju Treatment Plant.

The turnkey contractor entrusted the construction of civil and structural components of this all-important contract to Asia Baru Construction Sdn. Bhd. in recognition of their impeccable record in fast-track water supply projects.

The scope of work by Asia Baru Construction Sdn. Bhd. consisted of :-

a) 1 no. r.c. weir across Sungai Gombak for flow regulation.
b) 1 no. river intake.
c) 6 nos. roughing filters and balancing tank.
d) 1 no. 46 Mld. pumping station.
e) TNB substation and other ancillary structures.
f) Approximately 10 km of 700 mm diameter M. S. raw water pumping main long the Middle Ring Road II.
Project Information
Client / Owner: JKR (Cawangan Bekalan Air)
Consultant: SMHB Sdn. Bhd.
Main Contractor: Biwater Shellabear (M) Sdn. Bhd.
Sub-Contractor:
Date of Commencement: 15th July 1998
Date of Completion: 14th December 1998
Project Methodology
In order to achieve the tight deadline of commissioning the whole system in 5 months, teamwork was the order of the day.

Coordination meetings were conducted frequently to resolve problems effectively and hence, ensuring uninterrupted construction activities at site.