PROJECTS > Construction Of Water Treatment Plant And Equipment For The Development Of A Proposed Power Plant

Project Background
In the mid nineties due to the rapid expansion of the economy, Malaysia was experiencing a great shortage of electricity. This prompted the government to encourage the setting up of Independent Power Producers (IPP) to augment the production capacity of Tenaga Nasional, the sole supplier of electricity in Peninsular Malaysia. In responding to the government call, Genting Sanyen Power Sdn. Bhd. was one of the IPPs given the licence to generate 720 MW of electricity. Due to the urgency of the project, Genting Sanyen Power Sdn. Bhd. had decided to carry out the project on a fast-track basis. Amongst other power generating equipment and facilities, a water treatment plant was required to supply treated water to the power plant. Asia Baru Construction Sdn. Bhd. in association with Syarikat Ismail Ibrahim were appointed as the Civil and Building Contractor for the Water Treatment Plant in Kuala Langat, Selangor. The scope of work comprised the following:-

1) River intake upgrading works.

2) Grit removal chamber.

3) Raw water pipeline.

4) Cascade Aerator.

5) Flocculation tank and distribution channel.

6) Sedimendation tanks and settled water channel.

7) Filters and filter gallery.

8) Chemical and control building.

9) Pumping station.

10) 3.4 MG treated water reservoir.

11) 100,000 gal. back-wash tank.

12) Pipeworks and piperack.

13) Sludge holding tank.
Project Information
Client / Owner: Genting Sanyen Power Sdn. Bhd.
Consultant: Perunding EIA.
Main Contractor: Asia Baru Construction Sdn. Bhd./Syarikat Ismail Ibrahim Sdn. Bhd.
Sub-Contractor: CWM Engineering Sdn. Bhd.
Date of Commencement: 19th January 1995
Date of Completion: 15th August 1995
Project Methodology
In view of the urgent nature of work which need to be completed and commissioned in seven (7) months, the job was awarded by direct negotiation and to be carried out on a fast-track basis. Construction drawings were issued progressively by the designers as work progressed. Discussions were held between Client, Consultant, Contractors to ensure that designs are buildable and the construction experience of the Contractors were taken into consideration in the designs and detailing. The Resident Engineer was given the full authority to decide on construction details at the site and solved all constructional problems jointly with the Contractors. Site discussions were held daily to ensure nothing was in the way of the construction. The equipment contractor was also involved right from the start to ensure that civil work boxed-out and openings are in accordance to the equipment supplied.

In order to reduce the amount of piling work, the designer had decided to incorporate the 100,000 gal. capacity back-wash tank on top of the chemical storage building. This not only save time but also structural work and cost.

The works went on late into the night and after seven (7) months of hard work, close coordination and cooperation between all parties concerned, the work was finally completed and water started flowing through the system in time for the operation of power plant. Another mission accomplished by Asia Baru Construction Sdn. Bhd. to the satisfaction of the Client. Our little contribution in helping to alleviate the power shortage in the country.