Asia Baru Construction
 
We are in civil and building construction with particular specialisation in Water Works and Sewerage project ranging from sewerage treatment plant, river intakes, water treatment plants, storage tanks, reservoirs, pipe laying and major diversion...etc
 
 
 
 
PROJECTS > PROJEK KECEMASAN PEMINDAHAN AIR MENTAH DARI SKIM PAMER (SG. SELUYUT) KE EMPANGAN 'UPPER LAYANG'

Project Background
The Project is implemented by the State Government of Johor with the objective to transfer raw water from PAMER (Sg Seluyut Reservoir) to Upper Layang Dam.

The main components of the Project are as follows :-
(a) Detailed design and site investigation
(b) Procurement and construction of approximately 30km of 1300mm diameter Mild Steel Cement Lined pipeline.
(c) Construction of pipe jacking works across Jalan Kota Tinggi-Pengerang, Senai Desaru Expressway and Jalan Sg Tiram
(d) Construction of pipe overcrossing at Sg. Johor, Sg. Seluyut and Sg. Tiram
Project Information
Client / Owner: Unit Perancang Ekonomi Negeri Johor (UPENJ)
Consultant: SMHB Sdn Bhd
Main Contractor: Asia Baru Construction Sdn Bhd (Design & Build)
Sub-Contractor:
Date of Commencement: 1st June 2016
Date of Completion: 6th June 2017
Project Methodology