PROJECTS > PROJEK PEMBEKALAN AIR MENTAH LAYANG 2 FASA 2 DARIPADA EMPANGAN SELUYUT KE EMPANGAN UPPER LAYANG

Project Background
The Project is implemented by the State Government of Johor with the objective to have a second pipeline for transferring of raw water from Seluyut Dam to Upper Layang Dam.

The main components of the Project are as follows:-

1. Procurement and construction of 33km of DN 1300 mm mild steel cement lined pipes.

2. Construction of pipe jacking works across Senai-Desaru Expressway, Jalan Tiram and Jalan Kota Tinggi-Sg Rengit

3. Construction of pipe crossing at Sg Johor, Sg Seluyut and Sg Tiram.

4. Procurement, installation, testing and commissioning 3nos of 150Mld pumps at existing Seluyut Booster Pumping Station complete with surge suppression system and all associated mechanical and electrical works.
Project Information
Client / Owner: Unit Perancang Ekonomi Negeri Johor (UPENJ)
Consultant: SMHB Sdn Bhd
Main Contractor: Konsortium PDT - Asia Baru (Design & Build)
Sub-Contractor:
Date of Commencement: 12th February 2017
Date of Completion: 11th February 2019