Location: Sedili / Seluyut / Bukit Panjang, Johor
Raw Water Supply Project to Rapid (PAMER)

Projects

Raw Water Supply Project to Rapid (PAMER)

Previous
Next

Project Information

Sedili / Seluyut / Bukit Panjang, Johor

Client / Owner

PRPC Water Sdn Bhd [PETRONAS]

Consultant

SMHB Sdn Bhd

Main Contractor

Konsortium Asia Baru – PPC JV

Date of Commencement

7th March 2014

Date of Completion

3rd January 2017

The Pengerang Integrated Petroleum Complex (PIPC) is an initiative by the Johor State Government to develop an oil and gas hub in Pengerang. PIPC will house PETRONAS’s Refinery and Petrochemical Integrated Development (RAPID) project and a host of other oil and gas industries, enterprises and support facilities.

The raw water supply project to PIPC will be undertaken in two (2) phases where Phase 1 will deliver 260 Mld of raw water, while Phase 2 will double up the total raw water supply to 520 Mld.

Johor State Government has granted PRPC Water Sdn Bhd, a wholly owned subsidiary of Petronas the rights to develop Phase 1 of the raw water supply project to PIPC (up to the boundary of RAPID). This Phase 1 development is known as the Raw Water Supply Project to RAPID or “Projek Air Mentah RAPID” or “PAMER”, and will deliver 230 Mld of the raw water to RAPID and another 30 Mld to the Johore State Government’s water treatment plant at Sg. Lebam.

The raw water will be abstracted from Sg. Sedili Besar and pumped through a raw water pumping main to an off-river storage by impounding a storage reservoir at Sg. Seluyut. From the Seluyut impounding reservoir, the raw water is delivered by gravity via the draw-off tower to a Booster Pumping Station downstream of the impounding reservoir. From the Booster Pumping Station, the raw water is pumped to the Terminal Reservoir at Bukit Panjang some 56 km away. 230 Mld of the raw water will be supplied to the Terminal Reservoir and 30 Mld will be supplied to the water treatment plant at Sg. Lebam. From the Terminal Reservoir at Bukit Panjang, raw water will be fed to a water treatment plant at RAPID by gravity pipelines.

Location: Langat, Selangor
Proposed Development of Langat 2 Water Treatment Plant & Water Reticulation System in Selangor/ Ku

Projects

Proposed Development of Langat 2 Water Treatment Plant & Water Reticulation System in Selangor/ Ku

Previous
Next

Project Information

Langat, Selangor

Client / Owner

Pengurusan Air Aset Berhad (PAAB)

Consultant

SMHB Sdn Bhd in association with Ranhill Consulting Sdn Bhd & KTA Tenaga Sdn Bhd

Main Contractor

Asia Baru Construction Sdn Bhd

Date of Commencement

12th June 2019

Date of Completion

11th June 2021

A component of a major water supply project for Selangor and Kuala Lumpur to meet the water demand needs up to year 2025; under the Western Corridor Bulk Distribution Works to construct an 80 ML capacity reservoir at Bandar Kinrara, Puchong.

The scope of works includes:

  1. Preparation of platform for Phase 1 and Phase 2 reservoir
  2. Phase 1 – 80ML capacity Petaling Reservoir
  3. Switch Room
  4. Guard House
  5. Pipeworks and valves
  6. Reinforced Earth Wall
  7. Electrical, Instrumentation & Telemetry Works

Location: Kahang, Johor
Cadangan Pembinaan Loji Rawatan Air (LRA) Kahang Yang Baru Dan Sistem Agihan Air Daripada LRA Kahang

Projects

Cadangan Pembinaan Loji Rawatan Air (LRA) Kahang Yang Baru Dan Sistem Agihan Air Daripada LRA Kahang

Previous
Next

Project Information

Kahang, Johor

Client / Owner

Bahagian Perancang Ekonomi Negeri Johor (BPENJ)

Consultant

HLA Associates Sdn Bhd

Main Contractor

Konsortium PDT – Asia Baru

Date of Commencement

28th November 2017

Date of Completion

28th November 2020

A design and build project implemented by the State Government of Johor to provide additional treated water supply to Kluang District from the new Kahang Dam to ensure supply adequacy during the dry seasons and to meet future demand as well as to phase out old WTPs with unreliable raw water sources.

The project scope includes:

  1. Construction of a raw water Booster Pump Station of 90MLd capacity at Kahang Dam.
  2. Laying of 2.8km length of 1200mm dia. and 15km of 1000mm dia. MSCL pipelines.
  3. Construction of a water treatment plant of 90 MLd capacity with M&E works for an initial phase of 45 MLd capacity.
  4. Construction of two balancing reservoirs (Sembrong Timur 3) of 6.5ML capacity.
  5. Upon completion of raw water Booster Pump Station, provide O&M to supply raw water to an existing WTP then upon completion of WTP revert the raw water supply pipeline to a treated water pumping main for supply to the two balancing reservoirs.

Location: Kota Tinggi, Johor
Project Pembekalan Air Mentah Layang 2 Fasa 2 daripada Empangan Seluyut ke Empangan Upper Layang

Projects

Project Pembekalan Air Mentah Layang 2 Fasa 2 daripada Empangan Seluyut ke Empangan Upper Layang

Previous
Next

Project Information

Kota Tinggi, Johor

Client / Owner

Unit Perancang Ekonomi Negeri Johor (UPENJ)

Consultant

SMHB Sdn Bhd

Main Contractor

Konsortium PDT – Asia Baru (Design & Build)

Date of Commencement

12th February 2017

Date of Completion

11th February 2019

The Project is implemented by the State Government of Johor with the objective to have a second pipeline for transferring of raw water from Seluyut Dam to Upper Layang Dam.

The main components of the Project are as follows:-

  1. Procurement and construction of 33km of DN 1300 mm mild steel cement lined pipes.
  2. Construction of pipe jacking works across Senai-Desaru Expressway, Jalan Tiram and Jalan Kota Tinggi-Sg Rengit
  3. Construction of pipe crossing at Sg Johor, Sg Seluyut and Sg Tiram.
  4. Procurement, installation, testing and commissioning 3nos of 150Mld pumps at existing Seluyut Booster Pumping Station complete with surge suppression system and all associated mechanical and electrical works.

Location: Mersing, Johor
Project Kecemasan Penyaluran Air Mentah daripada Sg. Lenggor ke Empangan Congo

Projects

Project Kecemasan Penyaluran Air Mentah daripada Sg. Lenggor ke Empangan Congo

Previous
Next

Project Information

Mersing, Johor

Client / Owner

Unit Perancang Ekonomi Negeri Johor (UPENJ)

Consultant

Angkasa Consulting Services Sdn Bhd – Omni Project Consultancy Sdn Bhd Joint Venture

Main Contractor

Asia Baru Construction Sdn Bhd (Design & Build)

Date of Commencement

3rd October 2016

Date of Completion

14th June 2017

The Project is implemented by the State Government of Johor with the objective to transfer raw water from Sg Lenggor to Congok Dam, Mersing

The main components of the Project are as follows:-

  1. Detailed design and site investigation.
  2. Construction of an intake cum pump station and all associated works at Sungai Lenggor to cater for 2nos of 16Mld pumps.
  3. Construction of an 11kV TNB Sub-Station complete with all necessary mechanical & electrical works.
  4. Procurement and construction of approximately 33km of 600mm diameter Mild Steel Cement Lined pipeline.
  5. Construction of an outlet structure at Congok Dam.
  6. Construction of pipe jacking works across Jalan Kilang Sawit Nitar and Jalan Felda Nitar 2.
  7. Construction of pipe overcrossing at Sungai Mayang.

Location: Kota Tinggi, Johor
Projek Kecemasan Pemindahan Air Mentah dari Skim Pamer (Sg.Seluyut) ke Empangan Upper Layang

Projects

Projek Kecemasan Pemindahan Air Mentah dari Skim Pamer (Sg.Seluyut) ke Empangan Upper Layang

Previous
Next

Project Information

Kota Tinggi, Johor

Client / Owner

Unit Perancang Ekonomi Negeri Johor (UPENJ)

Consultant

SMHB Sdn Bhd

Main Contractor

Asia Baru Construction Sdn Bhd (Design & Build)

Date of Commencement

1st June 2016

Date of Completion

6th June 2017

The Project is implemented by the State Government of Johor with the objective to transfer raw water from PAMER (Sg Seluyut Reservoir) to Upper Layang Dam.

The main components of the Project are as follows :-

  1. Detailed design and site investigation
  2. Procurement and construction of approximately 30km of 1300mm diameter Mild Steel Cement Lined pipeline.
  3. Construction of pipe jacking works across Jalan Kota Tinggi-Pengerang, Senai Desaru Expressway and Jalan Sg Tiram
  4. Construction of pipe overcrossing at Sg. Johor, Sg. Seluyut and Sg. Tiram

Location: Pengerang, Johor
Temporary Saj Water Pipeline for Rapid Camp & Tanjung Pengelih Area

Projects

Temporary Saj Water Pipeline for Rapid Camp & Tanjung Pengelih Area

Previous
Next

Project Information

Pengerang, Johor

Client / Owner

PRPC Sdn Bhd [PETRONAS]

Consultant

SMHB Sdn Bhd

Main Contractor

Konsortium Asia Baru PPC JV

Date of Commencement

16th January 2015

Date of Completion

31st July 2015

This Project is implemented with the objective to supply treated water to RAPID workers camp as well as consumers at Tanjung Pengelih area. Treated water from Syarikat Air Johor (SAJ) source will be tapped from existing SAJ pipeline at KR road junction at Federal Road FT92 and conveyed through about 14.78km long of mild steel pipeline with nominal diameter DN 650/500mm.

The main components of the Project are as follows :-

  1. Hot Tapping and Pipe Jointing Works at FT92/KKR Road Junction and J52/Public Access road The Hot Tapping Works comprises pipe jacking across Federal Trunk FT92 inclusive of sleeves, grouting as per JKR requirements, hot tapping on to the existing 450mm diameter SAJ pipelines as per the SAJ requirements, provision of valves for subsequent disconnection and reconnection ; provision of valves for connection to Section 4 of PAMER pipeline and subsequent connection and disconnection to PAMER pipeline.
  2. Pipeline Works from FT92/KKR Road Junction to J52/Public Access Road Junction Procurement, testing at manufacturer’s works, delivery, installation, testing and commissioning for the potable water supply of approximately 10.5km of 650mm diameter Mild Steel Cement Lined pipeline from Syarikat Air Johor’s (SAJ) pipeline along Federal Trunk FT92/KKR Road Junction to tee-off to Temporary Camp Facilities and approximately 4km of 500mm diameter Mild Steel Cement Lined pipeline from tee-off to Temporary Camp Facilities to SAJ’s pipeline along J52/Public Access Road Junction.
  3. Hydrostatic Pressure and Leakage Testing Field hydrostatic pressure and leakage test, sterilization, flushing as required by Syarikat Air Johor, and everything else necessary for the supply of potable water from SAJ’s pipeline along FT92 Junction to SAJ’s pipeline along J52 Junction.
  4. Procurement, Construction and Commissioning of all valves, specials, fittings and flow meter as required by Syarikat Air Johor.

Location: Kahang, Johor
Projek Pembinaan Empangan Kahang

Projects

Projek Pembinaan Empangan Kahang

Previous
Next

Project Information

Kahang, Johor

Client / Owner

Jabatan Bekalan Air Kementerian Tenaga, Teknologi Hijau Dan Air

Consultant

HLA Associates Sdn Bhd

Main Contractor

Asia Baru Construction Sdn Bhd

Date of Commencement

15th May 2014

Date of Completion

14th May 2017

The works, “Projek Pembinaan Empangan Kahang di Daerah Kluang, Johor” forms part of the construction of the engineering works to meet the projected water demand in Kluang District.

Project scope of works include:

  1. Site clearing
  2. Construction of an earth fill dam with a capacity of 23 MCM with all necessary earth works, drilling & grouting, geotechnical instrumentation and turfing.
  3. Construction of an Inlet & Outlet Structure, Intake Tower, Spillway, Stilling Basin, Access Bridge, Transfer Culvert and Seepage Chamber.
  4. Construction of all support structures within Dam site comprising of an Administration Building, Valve House, TNB Substation, Guard House and Boat House.
  5. All piping works within the transfer culvert and laying of 1200mm diameter Raw Water Pipeline.
  6. Construction of 2.5 km Main Access Road to Dam site.
  7. All external works inclusive of drainage, sewerage works, fencing and potable water supply.
  8. All mechanical, electrical works and instrumentations works.

Location: Tambak Laut, Melaka
Pembinaan Loji Rawatan Kumbahan Serantau Bandaraya Melaka

Projects

Pembinaan Loji Rawatan Kumbahan Serantau Bandaraya Melaka

Previous
Next

Project Information

Tambak Laut, Melaka

Client / Owner

Jabatan Perkhidmatan Pembetungan Kementerian Tenaga, Teknologi Hijau Dan Air

Consultant

DNP Consult Sdn Bhd

Main Contractor

Asia Baru Construction Sdn Bhd

Date of Commencement

23rd August 2013

Date of Completion

16th May 2017

A Sewerage Treatment Plant (STP) with an ultimate capacity of 360,000 PE with Phase 1 constructed for 120,000 PE.

The plant is designed with SBR process to treat sewage to category 1 standard ‘A’ effluent as per Malaysian Sewerage Industry Guidelines (MSIG). Additional modules of the mechanized STP will be implemented in a later stage in tandem with the increase of sewage flow. Treated effluent is discharged to a receiving main drain located approximately 500m from the plant. Waste sludge is thickened and dewatered within the STP facility.

The Project comprises of the following components :-

  • Inlet Work
  • Secondary Screen Chamber
  • Grit and Grease Chamber
  • Flow Distribution Chamber
  • Balancing Tank
  • SBR Tanks
  • Disinfection Tank
  • Reclaimed Water Building
  • Sludge Holding Tank
  • Mechanical Sludge Thickener Facility

Location: Sendayan, Negeri Sembilan
Projek Sistem Bekalan Air untuk Pembangunan Seremban Barat, Negeri Sembilan

Projects

Projek Sistem Bekalan Air untuk Pembangunan Seremban Barat, Negeri Sembilan

Previous
Next

Project Information

Sendayan, Negeri Sembilan

Client / Owner

Pengurusan Aset Air Berhad (PAAB)

Consultant

PZK Sdn Bhd

Main Contractor

Asia Baru Construction Sdn Bhd

Date of Commencement

18th February 2013

Date of Completion

29th March 2014

The main components for the Project are as follows :-

  • Supply, deliver and lay 12km of 750mm diameter mild steel pipe from Kolam Imbangan Gadong to Tangki Sedutan at Nusari Bayu Sendayan
  • Pipe jacking works
  • Hot tapping works