The Jelutong Sewerage Treatment Plant was to be constructed on 14.7 hectares of reclaimed land and will treat the entire raw waste from Georgetown, Penang with an ultimate PE of 1.2 million.
The Energy, Water and Communications Ministry had awarded the Contract to WWE Holdings Berhad. Asia Baru Construction was appointed as a civil sub-contractor to construct the two (2) anaerobic digester tanks (20.0m dia. x 16.0m height) by Cipta Wawasan Maju Engineering Sdn. Bhd (CWM), the process turnkey contractor appointed by WWE Holdings Bhd.
The Letter of Acceptance (LoA) was issued to Asia Baru by CWM on 26th October 2006. The possession of site was on 3rd January 2006. Between the receipt of LoA and actual possession at site on 3/1/2006, a lot of preparatory works and planning at head office were carried out. Among them were: