Asia Baru Water Services Sdn Bhd, a 95% owned subsidiary of Asia Baru Construction Sdn Bhd, was incorporated in January 2016 to provide Operation and Maintenance (O&M) services of reservoir, dam, water treatment plant and raw water plant.
Projects undertaken by the Company include:-
Emergency Water Supply from Seluyut Dam to Lebam Dam – O&M Services for a 60 MLd capacity intake pump station using a duty & standby Genset for power supply – March 2016 to June 2016
- Client: PRPC Water S/B (Petronas)
- Period: March 2016 to June 2016
Procurement, Construction & Commissioning of Raw Water Supply Project to Rapid (PAMER) – O&M Services for the 260 MLd capacity pumping system to transfer water from Seluyut Dam to Lebam Dam – June 2016 to November 2016
- Client: PRPC Water S/B (Petronas)
- Period: June 2016 to November 2016
Pengoperasian dan Penyelenggaraan Loji Bekalan Air Mentah dari Sg. Layang ke Tg. Langsat bagi Bekalan Air kepada Bahru Stainless Sdn Bhd – O&M Services for an Intake Pump Station of 24 MLd capacity at Upper Layang Dam
- Client: Johor Special Water (JSW)
- Period: June 2017 – March 2021
Projek Kecemasan Penyaluran Air Mentah Daripada Sg. Lenggor Ke Empangan Congok, Mersing – Emergency O&M Services for an Intake Pump Station of 32 MLd capacity for the Sg. Lenggor – Congok Dam raw water transfer scheme.
- Client: July 2017 – Unit Perancang Ekonomi Negeri (UPEN) Johor/ Badan Kawalselia Air Johor (BAKAJ)
- Period: July 2017 – July 2018
Projek Pembekalan Air Mentah Layang 2 Fasa 2 daripada Empangan Seluyut ke Empangan Upper Layang – sharing a common facility with project PAMER (Petronas), to provide Emergency O&M Services for a 300 MLd capacity pumping system to transfer water from Seluyut Dam to Upper Layang Dam.
- Client: Bahagian Perancang Ekonomi Negeri (BPEN) Johor
- Period: April 2019 – October 2020
Cadangan Pembinaan Loji Rawatan Air (LRA) Kahang Yang Baru Dan Sistem Agihan Air Dari LRA Kahang ke Bandar Kluang, Johor – O&M Services for the 48 MLd capacity raw water booster pump station to supply raw water from Kahang Dam to Sembrong Timur Water Treatment Plant
- Client: Bahagian Perancang Ekonomi Negeri (BPEN) Johor
- Period: September 2018 – March 2021