Project Information

Kota Tinggi, Johor

Client / Owner

Unit Perancang Ekonomi Negeri Johor (UPENJ)

Consultant

SMHB Sdn Bhd

Main Contractor

Asia Baru Construction Sdn Bhd (Design & Build)

Date of Commencement

1st June 2016

Date of Completion

6th June 2017

The Project is implemented by the State Government of Johor with the objective to transfer raw water from PAMER (Sg Seluyut Reservoir) to Upper Layang Dam.

The main components of the Project are as follows :-

  1. Detailed design and site investigation
  2. Procurement and construction of approximately 30km of 1300mm diameter Mild Steel Cement Lined pipeline.
  3. Construction of pipe jacking works across Jalan Kota Tinggi-Pengerang, Senai Desaru Expressway and Jalan Sg Tiram
  4. Construction of pipe overcrossing at Sg. Johor, Sg. Seluyut and Sg. Tiram