Sendayan, Negeri Sembilan

Client / Owner

Pengurusan Aset Air Berhad (PAAB)

Consultant

PZK Sdn Bhd

Main Contractor

Asia Baru Construction Sdn Bhd

Date of Commencement

18th February 2013

Date of Completion

29th March 2014

The main components for the Project are as follows :-

  • Supply, deliver and lay 12km of 750mm diameter mild steel pipe from Kolam Imbangan Gadong to Tangki Sedutan at Nusari Bayu Sendayan
  • Pipe jacking works
  • Hot tapping works