Airport, Sepang, Selangor

Client / Owner

Malaysia Airport Holding Berhad

Consultant

SMHB Sdn Bhd

Main Contractor

Asia Baru Construction Sdn Bhd

Date of Commencement

14th May 2010

Date of Completion

31st March 2013

Malaysia Airport Holding Berhad called an open tender for the Proposed Development of New LCC Terminal and Associated Works At KL International Airport, Sepang, Selangor, Package UT01 – Water Distribution. Asia Baru Construction Sdn Bhd was successful in its bid and was awarded the Contract. The works under the Contract, when completed, will supply potable water to the new LCC Terminal (subsequently re-named as KLIA2) Airport by a branch-off tee from nearby existing 1000mm diameter pipeline.

Briefly, the scope of works under the Contract comprised the following major components:

  • Supply and lay 1000mm diameter mild steel pipe, approximately 6.3km long.
  • Supply and lay 600mm diameter mild steel pipe, approximately 6.1km long.
  • Pipejacking of 1500mm diameter RC sleeve as road crossing for 1000mm diameter mild steel pipe, 63m long.
  • All other associated ancillary works.